Wyoming State Land Negotiation Meeting
February 18th, 2009
We'll be negotiating terms with Wyoming State to lease some more land for possible development.
Platte County Zoning Review
June 19th, 2007
The Platte County commissioners will meet to approve or deny our application for a special use permit to erect an anemometer.
Anemometer Erection
July 2nd, 2007
The tower should go up in as little as one or two days. We should have data streaming by the end of the day.
Milestone |
Date |
|
| done | Chugwater Town Hall Meeting | March 5th, 2007 |
| done | Site inspection by Secor | March 10th, 2007 |
| done | Close on lease agreement for 1st wind study. | April 12th, 2007 |
| done | Submit special use permit request to Platte Co. | May 2nd, 2007 |
| done | Have zoning hearing board review | June 13th, 2007 |
| done | Hardware setup and data collection started | July 2nd, 2007 |
| done | Data Evaluation | December, 2007 |
| done | Title and Mineral Review | December, 2007 |
| done | Draft long term lease agreement | January, 2008 |
| missed | Become qualified bidder for WCI line | March, 2008 |
| done | Explore possible transmission solution, Tri State G&T | April, 2008 |
| done | Secure additional funding for the next 12 months | May, 2008 |
| done | Complete first year wind study | July, 2008 |
| done | Have a scoping meeting with Tri State G&T | August, 2008 |
| on hold | Negotiate land terms with Wyoming State | February, 2009 |
| done | Secure additional land leases | March, 2009 |
| on hold | Apply for WCI transmission space | March, 2009 |
| postponed | Apply for Excel RFP | April, 2009 |
| done | Erect second anemometer | October, 2009 |
| on hold | Start environmental impact studies | TBD |
| Negotiate PPA | TBD | |
| Order Turbines | TBD | |
| Begin Construction | April, 2013 | |
| Turn on turbines | September, 2013 |