Calendar of Events
This reflects a high level overview of where our current project is and what milestones are coming up.


Highlights

Platte County Zoning Review
June 19th, 2007
The Platte County commissioners will meet to approve or deny our application for a special use permit to erect an anemometer.

Anemometer Erection
July 2nd, 2007
The tower should go up in as little as one or two days. We should have data streaming by the end of the day.



Project Timeline

 

Milestone

Date

done Chugwater Town Hall Meeting March 5th, 2007
done Site inspection by Secor March 10th, 2007
done Close on lease agreement for 1st wind study. April 12th, 2007
done Submit special use permit request to Platte Co. May 2nd, 2007
done Have zoning hearing board review June 13th, 2007
done  Hardware setup and data collection started July 2nd, 2007
done  Data Evaluation December, 2007
done  Title and Mineral Review December, 2007
done  Draft long term lease agreement January, 2008
in progress Solicit Project Development Financing March, 2008
in progress Confirm community support March, 2008
  Draft permitting requirements to the state and county offices. April, 2008
  Complete environmental and road studies May, 2008
  Bid for power line capacity June, 2008
  Submit and RFP for project construction contracts July, 2008
  Complete first year complete wind study July, 2008
  Bid on PSCo's Request For Proposal for Wind power generation. September, 2008
  Order Turbines March, 2010
  Begin Construction March, 2012
  Turn on the turbines January, 2013