Calendar of Events
This reflects a high level overview of where our current project is and what milestones are coming up.


Highlights

Wyoming State Land Negotiation Meeting
February 18th, 2009
We'll be negotiating terms with Wyoming State to lease some more land for possible development.

Tri State Generation and Transmission Scoping Meeting
August 14th, 2008
The scoping meeting with Tri State G and T revelead that their process reform is being developed to handle the high load of requests and the fact that many hardware upgrades will be required to take advantage of this resource.

Platte County Zoning Review
June 19th, 2007
The Platte County commissioners will meet to approve or deny our application for a special use permit to erect an anemometer.

Anemometer Erection
July 2nd, 2007
The tower should go up in as little as one or two days. We should have data streaming by the end of the day.



Project Timeline

 

Milestone

Date

done Chugwater Town Hall Meeting March 5th, 2007
done Site inspection by Secor March 10th, 2007
done Close on lease agreement for 1st wind study. April 12th, 2007
done Submit special use permit request to Platte Co. May 2nd, 2007
done Have zoning hearing board review June 13th, 2007
done  Hardware setup and data collection started July 2nd, 2007
done  Data Evaluation December, 2007
done  Title and Mineral Review December, 2007
done  Draft long term lease agreement January, 2008
missed Become qualified bidder for WCI line March, 2008
done Explore possible transmission solution, Tri State G&T April, 2008
done Secure additional funding for the next 12 months May, 2008
done Complete first year wind study July, 2008
done Have a scoping meeting with Tri State G&T August, 2008
on hold Negotiate land terms with Wyoming State February, 2009
done Secure additional land leases March, 2009
on hold Apply for WCI transmission space March, 2009
postponed Apply for Excel RFP April, 2009
done Erect second anemometer October, 2009
on hold Start environmental impact studies TBD
  Negotiate PPA TBD
  Order Turbines TBD
  Begin Construction April, 2013
  Turn on turbines September, 2013